Topic: CDM
How to appoint a Principal Contractor under CDM 2015
On a project where more than one contractor is, or is reasonably foreseeable to be, working at any time, the client must appoint a Principal Contractor in writing. The appointment should not be treated as an administrative formality. The client needs to identify the contractor that will genuinely control the construction phase, check that it has the capability and resources for the role, make the appointment early enough, and ensure the written appointment matches the way the project will actually be managed.
- Published
- Updated
- 8 min read

Free template
Principal Contractor Appointment Letter
Download our editable one-page Word template for recording a written Principal Contractor appointment under CDM 2015.
Editable .docx · 1 page · No sign-up required
General guidance and example content. Not legal advice or a guarantee of compliance.
When must a Principal Contractor be appointed?
Regulation 5 applies where more than one contractor is, or is reasonably foreseeable to be, working on the project at any time. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
In that situation, the client must appoint a contractor as Principal Contractor in writing. The appointment should be made as soon as practicable and before the construction phase begins. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
Who makes the appointment?
On a commercial project, the client makes the Principal Contractor appointment. HSE guidance for commercial clients: HSE summary of commercial client appointment and assurance responsibilities under CDM 2015 (opens in a new tab)
The client can take advice from project managers, health and safety advisers or the Principal Designer, but responsibility for making the required appointment remains with the client. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
Step 1: confirm whether the role is required
The first question is whether the project will involve more than one contractor at any time, including where additional contractors are reasonably foreseeable. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
This is broader than asking whether several contractors will be on site at exactly the same moment. If the project structure involves multiple contractors across the construction phase, the Principal Contractor appointment should be planned accordingly. The CDM duty-holder map sets out which appointments a project of that shape needs.
Step 2: identify the contractor that will genuinely control the construction phase
The Principal Contractor must be a contractor. The client should identify the contractor with the authority and practical control needed to plan, manage, monitor and coordinate the construction phase. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
The commercial title is not decisive. The ‘main contractor’ is often the Principal Contractor, but not automatically. The appointment should match the actual management structure. HSE guidance for principal contractors: HSE summary of principal contractor appointment and responsibilities under CDM 2015 (opens in a new tab)
Step 3: assess capability before appointment
Before appointment, the client should take reasonable steps to satisfy itself that the proposed contractor has the skills, knowledge and experience required for the role and, where an organisation is appointed, appropriate organisational capability. Read Regulation 8 on legislation.gov.uk: skills, knowledge and experience, and organisational capability for organisations (opens in a new tab)
Useful evidence may include:
- Experience on projects of comparable scale, complexity and risk.
- Construction-phase management and coordination experience.
- Adequate management and supervisory resources.
- Arrangements for planning, monitoring and reviewing construction work.
- Systems for contractor coordination and interface management.
- Site induction, worker consultation and welfare arrangements.
- Health and safety performance information and references.
- Relevant qualifications, training and continuing professional development as supporting evidence.
No single qualification, certificate, accreditation or membership automatically proves suitability for a specific project. Read Regulation 8 on legislation.gov.uk: skills, knowledge and experience, and organisational capability for organisations (opens in a new tab)
Step 4: make the appointment early enough
The Principal Contractor needs time before construction starts to plan the construction phase, develop the construction phase plan, establish site arrangements, coordinate contractors and prepare for mobilisation. HSE L153 guidance: HSE guidance on CDM 2015 appointments, capability and project management arrangements (opens in a new tab)
A last-minute appointment may exist on paper but leave too little time for the role to be performed properly.
Step 5: make the appointment in writing
Regulation 5 requires the Principal Contractor appointment to be in writing. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
CDM 2015 does not prescribe a statutory appointment-letter template. The written appointment should make the role and its effective date clear and should align with the actual contract and project-management structure. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
If you need a simple written record of the appointment, download our free Principal Contractor Appointment Letter template.
What should a Principal Contractor appointment letter cover?
CDM 2015 requires the appointment to be in writing but does not prescribe a standard form. A straightforward written appointment should make the appointment unambiguous by identifying: Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
- The client making the appointment.
- The organisation appointed as Principal Contractor.
- The project the appointment relates to.
- The date the appointment takes effect.
- A clear statement that the organisation is appointed as Principal Contractor under the Construction (Design and Management) Regulations 2015.
The letter may also:
- Acknowledge that the Principal Contractor’s statutory duties arise under CDM 2015.
- Record who signed it on behalf of the client, and in what role.
- Include an acknowledgement of receipt from the Principal Contractor, if the parties want one.
Detailed project scope, programme, interfaces, information requirements and management arrangements can be dealt with through the contract, pre-construction information, Construction Phase Plan and other project documentation where appropriate. They can still be included in the letter if that suits the project, but they are not needed to make a straightforward written appointment clear.
Does the appointment letter transfer the client’s duties?
No. Appointing a Principal Contractor gives that contractor its own statutory Principal Contractor duties. It does not transfer away the commercial client’s separate duties under CDM. HSE guidance for commercial clients: HSE summary of commercial client appointment and assurance responsibilities under CDM 2015 (opens in a new tab)
The client must continue to maintain and review the project-management arrangements and take reasonable steps to ensure the Principal Contractor carries out the duties specified by Regulation 4. Read Regulation 4 on legislation.gov.uk: client duty to make and maintain suitable arrangements for managing the project and to take reasonable steps to ensure the principal designer and principal contractor carry out their duties (opens in a new tab)
What information should the client provide at appointment?
The Principal Contractor needs enough project information to plan the construction phase effectively. HSE L153 guidance: HSE guidance on CDM 2015 appointments, capability and project management arrangements (opens in a new tab)
This may include:
- Relevant pre-construction information.
- The client brief and project requirements.
- Known site and asset constraints.
- Existing surveys, drawings and service information.
- Known health and safety file information where relevant.
- Programme and sequencing requirements.
- Design information available at the time of appointment.
- Client governance, reporting and escalation arrangements.
How should the Principal Designer and Principal Contractor appointments align?
On projects involving more than one contractor, the client appoints both a Principal Designer and a Principal Contractor. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
The appointments should support a clear handover from pre-construction coordination into the construction phase, with suitable information flowing between the Principal Designer and Principal Contractor. HSE L153 guidance: HSE guidance on CDM 2015 appointments, capability and project management arrangements (opens in a new tab)
Unclear overlaps or gaps between the two appointments can weaken coordination at exactly the point where design decisions are becoming construction activities.
What happens if the client fails to appoint a Principal Contractor?
If Regulation 5 requires a Principal Contractor and the client fails to appoint one, the appointment duty does not disappear. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
The client must itself fulfil the Principal Contractor duties in Regulations 12 to 14. Read the regulations on legislation.gov.uk: Regulations 12 to 14: the construction phase plan and health and safety file, principal contractor duties during the construction phase, and worker consultation and engagement (opens in a new tab)
This is not a substitute for making a proper appointment where one is required; it is the statutory consequence of the client’s failure to appoint. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
What about domestic clients?
Domestic-client projects have different arrangements under Regulation 7. Read Regulation 7 on legislation.gov.uk: domestic-client arrangements and transfer of specified client duties (opens in a new tab)
Where there is only one contractor, that contractor carries the specified domestic-client duties. Read Regulation 7 on legislation.gov.uk: domestic-client arrangements and transfer of specified client duties (opens in a new tab)
Where there is more than one contractor, the Principal Contractor carries the specified domestic-client duties. If the domestic client does not appoint a Principal Contractor, the contractor in control of the construction phase carries the Principal Contractor role. Read Regulation 7 on legislation.gov.uk: domestic-client arrangements and transfer of specified client duties (opens in a new tab)
A domestic client may also make a written agreement with the Principal Designer for specified client duties. These arrangements should not be collapsed into a generic ‘contractor or Principal Designer’ rule. Read Regulation 7 on legislation.gov.uk: domestic-client arrangements and transfer of specified client duties (opens in a new tab)
Can the appointment be included in the main contract?
Yes, provided the appointment is clear and in writing. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
The CDM appointment may sit within a building contract, professional agreement, letter of appointment or another written instrument. The important point is that the statutory role, appointee and effective date are unambiguous.
Can the appointment be conditional?
Commercial contracts sometimes contain conditions or staged appointments. Care is needed if those arrangements mean the Principal Contractor role is unclear when construction begins.
The client should be able to identify who holds the statutory role at the relevant time. A conditional or future appointment should not leave the construction phase without a Principal Contractor when Regulation 5 requires one. Read Regulation 5 on legislation.gov.uk: client duty to appoint a designer as principal designer and a contractor as principal contractor in writing where more than one contractor is, or is reasonably foreseeable to be, working on the project, and the consequence of failing to appoint (opens in a new tab)
Can the Principal Contractor appointment change during the project?
Yes. If the appointed Principal Contractor changes, the client should make the new appointment clearly and manage the transition.
Relevant information, the construction phase plan, outstanding actions, contractor interfaces and site-management arrangements should transfer effectively so that coordination is not interrupted. HSE L153 guidance: HSE guidance on CDM 2015 appointments, capability and project management arrangements (opens in a new tab)
Common Principal Contractor appointment mistakes
Treating the appointment as a signature exercise
The client checks the letter but not whether the contractor actually has control, resources and capability.
Assuming the main contractor automatically holds the role
Commercial naming does not replace a clear statutory appointment.
Appointing after mobilisation has already started
The contractor loses valuable time to plan the construction phase and establish suitable arrangements.
Using capability evidence that is too generic
Company certificates and policies are reviewed without checking comparable project experience or available resource.
Using a template that does not match the contract
The letter says one organisation is Principal Contractor while the contract gives practical control to another.
Leaving the effective date unclear
The project team cannot tell exactly when the statutory role starts.
Treating the appointment as transfer of client responsibility
The commercial client’s own CDM duties remain in place.
Principal Contractor appointment checklist
A simple letter can record the written appointment; making a suitable appointment still requires the wider client duties and checks described in this guide. Use this checklist for the whole appointment process:
- Confirm more than one contractor is or is reasonably foreseeable.
- Identify the contractor that will genuinely control the construction phase.
- Check project-specific skills, knowledge and experience.
- Check organisational capability where an organisation is appointed.
- Check management and supervisory resources.
- Make the appointment early enough for mobilisation and CPP development.
- Make the appointment in writing.
- State the effective date clearly.
- Align the appointment with the commercial contract and project structure.
- Provide relevant pre-construction information.
- Confirm interfaces with the Principal Designer and client.
- Keep the arrangements under review if the project structure changes.
Example Principal Contractor appointment structure
The free Aptoris template follows this simple structure on a single page. It is a practical format, not a prescribed form: CDM 2015 does not require any particular template.
1. Client and Principal Contractor
- The client making the appointment
- The organisation appointed
2. Project and effective date
- Project name or description
- Date of letter and effective date
3. Written appointment statement
- Appointed as Principal Contractor under regulation 5(1)(b) of CDM 2015
4. Brief CDM duty statement
- Duties arise under CDM 2015
- Does not replace or vary any contract
5. Client signature
- Signatory name and role
- Signature and date
6. Principal Contractor acknowledgement
- Acknowledgement of receipt
- Signature and date
Frequently asked questions
Who appoints the Principal Contractor under CDM 2015?
On a commercial project, the client appoints the Principal Contractor in writing where more than one contractor is, or is reasonably foreseeable to be, involved.
When should the Principal Contractor be appointed?
As soon as practicable and before the construction phase begins, so there is enough time to plan and establish the construction-phase arrangements.
Does the Principal Contractor appointment have to be in writing?
Yes. Regulation 5 requires the appointment to be in writing.
Is there a statutory Principal Contractor appointment-letter template?
No. CDM 2015 requires a written appointment but does not prescribe one standard letter or form.
What information needs to be in a Principal Contractor appointment letter?
CDM 2015 does not prescribe the content. A clear letter identifies the client, the organisation appointed, the project and the effective date, and states that the organisation is appointed as Principal Contractor under CDM 2015. Wider arrangements can sit in the contract and other project documents.
Does the Principal Contractor have to sign the appointment letter?
CDM 2015 requires the client to make the appointment in writing. It does not require the Principal Contractor to sign the letter, although a signed acknowledgement of receipt can be a useful record.
Can the appointment be included in the building contract?
Yes, provided the Principal Contractor role and effective date are clear in writing.
Does appointing a Principal Contractor transfer the client’s CDM duties?
No. The Principal Contractor takes on its own duties; the commercial client retains its separate client duties.
What happens if the client fails to appoint a Principal Contractor?
Where Regulation 5 requires one, the client must itself fulfil the Principal Contractor duties in Regulations 12 to 14.
Can the Principal Contractor change during the project?
Yes, but the client should make the replacement appointment clearly and manage the transfer of plans, information and coordination arrangements.
Is there a free Principal Contractor appointment letter template?
Yes. You can download our free one-page Word template to record a written Principal Contractor appointment under CDM 2015. It is a practical template, not a prescribed form, so adapt it to the project.