Construction Phase Plan Example: A Completed Plan for a Domestic Extension

A completed construction phase plan for a fictional single-storey rear extension to an occupied home. It shows what proportionate, project-specific entries can look like. It is not a plan for your project: use it to learn from, then assess your own work and write your own plan.

The project at a glance

All of the people, companies and the address are invented. The plan is shown at revision 1.2, part-way through the works.

Project
Single-storey rear extension, approx. 24 m², to a 1970s semi-detached house
Location
Harrogate, North Yorkshire (fictional address)
Programme
11 weeks, 55 working days, Monday to Friday
Workforce
Planned peak of 6 workers on site; about 232 person-days
Occupied home
A family of four lives in the house throughout the works
Client
Domestic clients; their client duties are carried out by the Principal Contractor
Duty holders
Principal Designer (architect), structural engineer, Principal Contractor and five contractors
F10 notification
Not notifiable: worked check included
Key work
Conservatory removal, trench-fill foundations, timber frame, cold-applied flat roof, opening the rear wall on temporary props for a steel beam
Schedule 3
Considered; no category applies, with the steel beam assessed as a precaution

Preview the completed plan

Real pages from the PDF.

The example follows the 17 sections of the Aptoris construction phase plan template, with every entry completed for one fictional project. It runs to 18 pages, and each one is marked as an illustrative example.

  • Project Information page of the completed example, with the project details, description and the F10 notification check showing the project is not notifiable
    Project Information and F10 check
  • Project Team and Duty Holders page of the completed example, with the duty holder matrix, key site personnel and the domestic client arrangements under regulation 7
    Project Team & Duty Holders
  • First Significant Site Risks page of the completed example, covering the conservatory removal, existing services, excavations, the temporary works for opening the rear wall and lifting the steel beam
    Significant Site Risks
  • Monitoring and Review page of the completed example, with the inspection schedule and the triggers that led to revisions 1.1 and 1.2
    Monitoring & Review

Swipe to see more pages.

View or download the example (PDF) (PDF, 18 pages, 976 KB)

Section by section: why these entries work

Short extracts from the completed plan, with a note on what each one shows. The full wording is in the PDF.

  1. 03 · Project Information

    The F10 check shows its working

    From the plan
    Result: not notifiable to HSE. Both parts of the first test must be met, and the person-day estimate is well below 500. Checked by D. Firth on 18/05/2026 from the programme and labour plan; re-checked at each revision.

    Why this works:

    Both parts of the first test have to be met, so the entry records each one and the person-day estimate behind it, then says the plan is still required. Check your own project with the F10 Notification Calculator; notification and the plan are separate questions.

  2. 04 · Project Team & Duty Holders

    The domestic client arrangement is stated, not assumed

    From the plan
    There is no written agreement for the Principal Designer to carry out the client duties, so the client duties in regulations 4(1) to (7) and 6 are carried out by Kestrelmoor Construction Ltd as Principal Contractor (regulation 7(1)(b)), in addition to its own duties.

    Why this works:

    On a domestic project the client duties pass to someone else. The plan names who that is and why, so nobody has to guess. See how CDM applies to domestic projects.

  3. 05 · Management Arrangements

    Arrangements describe what actually happens

    From the plan
    Example: on 14/07/2026 the existing lintel was found to differ from the drawings; work on the opening stopped until Ravenhowe issued TW-01 rev B.

    Why this works:

    The design-information entry says who issues what, how questions go back to the designer, and gives a real instance. That is more useful than a statement that "design information will be shared". The Principal Designer's role is to feed this information into the plan.

  4. 06 · Site Rules

    Rules written for this site

    From the plan
    This is an occupied family home. The household uses the front door and front path only. Keep the side gate to the rear works area locked; it is never left open, even briefly.

    Why this works:

    Generic rules such as PPE and signing in are there, but the rules that matter most are the ones only this site needs: the household, the children and the locked gate.

  5. 09 · Emergency Procedures

    Emergency details someone can act on

    From the plan
    Dial 999. Give the site address, 4 Sallowby Grove, Harrogate, and say that vehicle access is from the street via the driveway. The Site Manager sends someone to the street to meet the ambulance or fire service.

    Why this works:

    The entry names the nearest 24-hour Emergency Department, who is in charge, and the gas emergency number to call after a pipe strike. On a real project the team confirms these details for its own site before work starts.

  6. 12 · Significant Site Risks

    Significant risks only, with a hold point where it matters

    From the plan
    Before the wall is cut, the Site Manager checks the installation against the design and signs the permit to load. Props stay until the steel is bedded and the engineer's curing period has passed; removal is authorised by the Site Manager.

    Why this works:

    The table covers the risks that are significant on this job and points to the contractors' RAMS for task detail rather than copying them in: HSE guidance warns against filling the plan with generic risk assessments or method statements.

  7. 12 · Schedule 3

    A considered conclusion, recorded

    From the plan
    The single steel beam (approx. 3.6 m, approx. 120 kg) was assessed against item 10, the assembly of heavy prefabricated components. As a precaution, the specific measures for that task are recorded in this section: engineer-designed temporary props, the permit to load, the lifting method and the closure of the kitchen.

    Why this works:

    The plan explains why no Schedule 3 category is considered to apply, and where a reasonable reader might disagree it records the specific measures anyway.

  8. 12 · Significant Site Risks

    Planning out a hazard, for this job

    From the plan
    Hot work designed out for this project by choosing a cold-applied liquid membrane. Fellacre Roofing's COSHH assessment and the product safety data sheet are on site; skin and eye protection worn; containers kept closed in the lockable store.

    Why this works:

    Choosing a cold-applied roof removed hot work from this project, but it brought a chemical product to manage instead. The entry records both. It is a choice made for this job, not a rule for every roof.

  9. 13 · Traffic Management: highway and footpath works

    N/A, with a reason

    From the plan
    N/A: no skip, scaffold, materials or plant on the highway or footpath. The skip sits on the driveway.

    Why this works:

    Where something genuinely does not apply, a short N/A with the reason is better than an invented hazard or a blank box.

  10. 02 · Document Control: revision 1.2

    A living document

    From the plan
    Revised before the existing rear wall is opened: temporary works design TW-01 rev B, kitchen closure arrangements for the household and re-briefing of everyone on site.

    Why this works:

    The revision history shows the plan changing as the work changes. Each revision is tied to a trigger listed in section 16. A plan must be reviewed, updated and revised throughout the project.

What information should be in a construction phase plan?

What CDM 2015 requires

Regulation 12(2) says the plan must set out the health and safety arrangements and site rules for the construction phase, taking account where necessary of industrial activities on the site, and, where applicable, specific measures for work in the Schedule 3 categories.

HSE's guidance (L153, Appendix 3) lists the topics a plan should consider, including a description of the project and key dates, the management arrangements, site rules, cooperation and coordination, worker involvement, site induction, welfare, fire and emergency procedures, and the control of significant risks.

Read what a construction phase plan should contain

How the Aptoris template organises it

The law does not prescribe headings. The Aptoris template, and this example, arrange the requirements into 17 sections:

  1. 1Document map
  2. 2Document control
  3. 3Project information
  4. 4Project team & duty holders
  5. 5Management arrangements
  6. 6Site rules
  7. 7Site induction
  8. 8Welfare
  9. 9Emergency procedures
  10. 10First aid
  11. 11Accident & incident reporting
  12. 12Significant site risks
  13. 13Traffic management
  14. 14RAMS management
  15. 15Environmental controls
  16. 16Monitoring & review
  17. 17Project sign-off

What you need to change for your own project

Do not copy entries from the example into a real plan. Every one of these depends on your project and must come from your own assessment of it:

  • Project details, programme and working hours
  • Who the duty holders are, and who carries out any domestic client duties
  • The F10 check: your duration, peak workforce and person-days
  • The significant risks and how you will control them
  • Existing services and asbestos information for your building
  • Temporary works, sequencing and any hold points
  • Access, scaffold and other work-at-height arrangements
  • Site access, deliveries and segregation from anyone else using the property
  • Welfare facilities and where they are
  • Emergency arrangements, including the nearest Emergency Department, confirmed for your site
  • First aid cover for your workforce
  • Monitoring, review triggers and who owns the plan

Keep the plan proportionate

HSE guidance says the plan should be as simple as possible and proportionate to the scale and complexity of the project and the risks involved. It should not be filled with generic risk assessments or detailed method statements that get in the way of understanding it.

This example is deliberately complete enough to learn from. A simpler job may need much shorter entries. For small projects HSE's leaflet CIS80 says a simple plan before the work starts is usually enough to show you have thought about health and safety.

Does a small project still need a construction phase plan?

Construction phase plan example FAQs

  • Can I copy this completed construction phase plan?

    No. Every entry describes a fictional project. Use it to see what a completed plan can look like, then prepare your own with the free editable Word template, replacing everything with your project's own information, risks and arrangements.

  • Does every construction project need a construction phase plan?

    Yes. Under CDM 2015 a construction phase plan is needed for every construction project, before the construction phase begins, whatever its size and whether or not it is notifiable. See when a construction phase plan is required.

  • Who prepares the construction phase plan?

    Where there is more than one contractor, the Principal Contractor draws it up, or arranges for it to be drawn up, during the pre-construction phase and before setting up the site. Where there is only one contractor, that contractor does. On a domestic project the client's duty to make sure a plan is in place is carried out by the contractor or Principal Contractor, unless there is a written agreement with the Principal Designer. See who prepares the plan.

  • Does a small domestic project need one?

    Yes, where the work is a construction project under CDM 2015. It can be short and simple. See domestic projects and the construction phase plan.

  • Can I download this construction phase plan example as a PDF?

    Yes. The example is a free PDF of 18 pages, with no sign-up or email needed. It is not offered as an editable Word file, so that fictional details are not carried into real plans. The editable version is the blank construction phase plan template.

Start your own plan with the blank template, and use the guide for the detail behind each section.

Write the plan for your own project

Use the free editable Word template. Every section has guidance on what to include, so you can build a plan around your own project, risks and arrangements.