Aptoris

Free Word checklist

Free Construction Phase Plan Checklist

A practical, editable Word checklist for reviewing whether a Construction Phase Plan is project-specific, proportionate, communicated and kept up to date under CDM 2015.

  • For single-contractor and multi-contractor projects
  • A CPP is required whether or not the project is F10-notifiable
  • Reviews suitability, site rules, significant risks, Schedule 3 and updates
  • A review aid, not the CPP itself, an approval certificate, RAMS or a site-inspection form
Download the Word checklist (Word document, 252 KB, Aptoris-Construction-Phase-Plan-Checklist.docx)

Editable .docx, 12 pages, No sign-up required

  • CPP requirement & responsibilityCheck that the plan is being prepared by the correct dutyholder and is in place at the required stage.
  • Arrangements & site rulesReview whether the plan clearly explains how the construction phase will be managed and which site rules apply.
  • Significant risks & Schedule 3Check that significant project risks and any applicable Schedule 3 measures are addressed.
  • Communication & reviewReview how the plan is communicated, implemented and kept current as the project changes.

Is a Construction Phase Plan required on every project?

A Construction Phase Plan is required for every construction project to which CDM 2015 applies.

  • That includes single-contractor and multi-contractor projects.
  • F10 notification status does not determine whether a Construction Phase Plan is required.
  • Construction Phase Plan

    Required under Regulations 4, 12 and 15, for the client, the Principal Contractor and the contractor on a single-contractor project.

  • F10 notification

    A separate Regulation 6 requirement to notify HSE of projects above the thresholds. It does not decide whether a plan is needed.

Check the thresholds with the F10 Notification Calculator

Sources: CDM 2015 regulation 4(5)(a) (opens in a new tab), regulation 6 (opens in a new tab), regulation 12(1) (opens in a new tab) and regulation 15(5) (opens in a new tab). The Construction Phase Plan guide explains when a plan is required.

Who prepares the Construction Phase Plan?

  • Multi-contractor project

    The Principal Contractor must draw up the plan, or make arrangements for it to be drawn up, during the pre-construction phase and before setting up the construction site.

    Regulation 12(1)

  • Single-contractor project

    The contractor must draw up the plan, or make arrangements for it to be drawn up, as soon as is practicable before setting up the construction site.

    Regulation 15(5)

  • Client

    The client must ensure that a Construction Phase Plan has been drawn up before the construction phase begins.

    Regulation 4(5)(a)

On a multi-contractor project, the Principal Designer assists the Principal Contractor by providing relevant information. The Principal Designer does not prepare or approve the CPP.

Sources: CDM 2015 regulation 4(5)(a) (opens in a new tab), regulation 12(1) and (3) (opens in a new tab) and regulation 15(5) (opens in a new tab).

When does the Construction Phase Plan need to be in place?

CDM 2015 sets three separate timing provisions, one for each duty holder.

  1. Client

    Before the construction phase begins.

    Regulation 4(5)(a)

  2. Principal Contractor

    During the pre-construction phase and before setting up the construction site.

    Regulation 12(1)

  3. Single contractor

    As soon as is practicable before setting up the construction site.

    Regulation 15(5)

Sources: CDM 2015 regulation 4(5)(a) (opens in a new tab), regulation 12(1) (opens in a new tab) and regulation 15(5) (opens in a new tab).

Does the client have to approve the Construction Phase Plan?

CDM 2015 does not prescribe a formal client approval certificate or CPP sign-off.

The client must ensure the CPP is drawn up before the construction phase begins. On a multi-contractor project, the client must also take reasonable steps to ensure the Principal Contractor complies with Regulations 12 to 14.

HSE guidance says the client must ensure that the plan adequately addresses the arrangements for managing the risks and that the Principal Contractor — or contractor on a single-contractor project — regularly reviews and revises it so it remains fit for purpose.

A project may still use internal or contractual review / approval arrangements.

Sources: CDM 2015 regulation 4(5)(a) and 4(6) (opens in a new tab); HSE L153 (opens in a new tab), Appendix 3, paragraph 8. The checklist’s completed / reviewed record is not a sign-off.

What changes for a domestic client?

Regulation 7 transfers the domestic client’s duties to another duty holder:

  • Single contractor

    The contractor carries out the relevant client duties.

  • More than one contractor

    The Principal Contractor carries them out.

  • Written agreement

    The Principal Designer may agree in writing to fulfil them.

This does not remove the contractor’s or Principal Contractor’s own CPP responsibilities under Regulations 15 or 12. The householder is not expected to approve the plan.

Source: CDM 2015 regulation 7(1) (opens in a new tab). See does CDM apply to domestic projects?

Preview the Construction Phase Plan Checklist

Twelve pages: project details, CPP set-up, eleven numbered review sections with a Schedule 3 table, a practical final review, outstanding actions, key references and a completed / reviewed record.

These are real pages from the Word checklist. Each check has tick boxes (Done, Reviewed / current or Checked) and N/A, with space for the evidence, reference or action behind it. The blue guidance box can be deleted before issue.

Page with the Schedule 3 table, work involving particular risks, introduced by the Regulation 12(2) requirement and the note that ticking No means no Schedule 3-specific measure is required for that category solely under Regulation 12(2), with Yes, No and To confirm tick boxes, a specific measures in CPP tick box and a reference column for each of the ten categories, a note that Schedule 3 is not a complete list of construction risks, and the start of section 9, supporting information and other project documents
Schedule 3 particular risksOpen full-size page: Schedule 3 particular risks (opens in a new tab)

Schedule 3 · Particular risks

Schedule 3 particular risks

  • All ten Schedule 3 categories, each with Yes, No and To confirm
  • A tick box for specific measures in the CPP, and a reference column
  • Tick No where a category does not apply; other significant risks still need managing
  • A note that Schedule 3 is not a complete list of construction risks

Swipe to see more pages.

Final page with a key references table for the CPP reference and revision, Pre-Construction Information reference, latest review or revision record, Principal Contractor and Principal Designer appointments where applicable and key supporting document references, a completed and reviewed by record, and a note that CDM 2015 does not prescribe a formal approval certificate or signature block for the CPP
Key references and recordOpen full-size page: Key references and record (opens in a new tab)

Key references · Completed record

Key references and record

  • The CPP reference, current revision and latest review or revision record
  • Pre-Construction Information and appointment references, where applicable
  • Key significant-risk and supporting document references
  • A completed / reviewed record, with no statutory sign-off

What the checklist covers

  • Project and CPP set-up
  • Requirement, responsibility and timing
  • Suitability and proportionality
  • Project description and key information
  • Management of the construction phase
  • Site rules
  • Information, induction and worker engagement
  • Welfare, access and emergency arrangements
  • Significant construction-phase risks
  • Schedule 3 particular risks
  • Supporting information and other project documents
  • Communication and implementation
  • Review, update and revision
  • Practical final review
  • Outstanding CPP actions
  • Key references
  • Completed / reviewed record

What makes a suitable Construction Phase Plan?

HSE guidance says the plan is the basis for communicating the construction-phase arrangements to everyone involved, so it should be easy to understand. The checklist reviews whether the plan is:

Source: HSE L153 (opens in a new tab), Appendix 3, paragraphs 3 and 4. No scoring: each item is reviewed and ticked.

  • Project-specific
  • Relevant
  • Sufficiently detailed
  • Proportionate
  • Understandable
  • Practical
  • Usable

Relevant, proportionate and as simple as possible

A longer Construction Phase Plan is not automatically a better plan.

HSE guidance says the plan should:

  • Be relevant to the project
  • Contain enough detail to explain the arrangements, site rules and necessary special measures
  • Remain proportionate to the scale, complexity and risks involved

A CPP should not become a document archive

HSE guidance specifically warns against including material that gets in the way of a clear understanding of what is needed to manage the construction phase. Its examples are:

Source: HSE L153 (opens in a new tab), Appendix 3, paragraph 4.

  • Generic risk assessments
  • Records of how decisions were reached
  • Detailed safety method statements

Risk assessments, method statements and RAMS may still be necessary for particular work. They can support the CPP without being indiscriminately copied into it.

What should a Construction Phase Plan cover?

Proportionate to the project, the checklist reviews what the plan records in four areas:

  • Project

    • Description
    • Relevant scope
    • Key programme information
    • Project team
    • Relevant site / operational context
  • Management arrangements

    • Planning
    • Management
    • Monitoring
    • Coordination
    • Cooperation
    • Contractor interfaces
    • Design changes
    • Communication
  • Site arrangements

    • Site rules
    • Induction
    • Information / instruction
    • Welfare
    • Security
    • Access
    • Emergency arrangements
  • Significant risks

    • Project-specific significant risks
    • How they will be managed
    • Relevant information from PCI / designers
    • Applicable Schedule 3 measures

Sources: CDM 2015 regulation 12(2) (opens in a new tab); HSE L153 (opens in a new tab), Appendix 3, paragraph 5. Not a hazard library: what is relevant depends on the project.

Site rules should be specific to the project

Regulation 12(2) requires the CPP to set out the site rules. Depending on the site, examples may include:

  • PPE
  • Parking
  • Radios / mobile phones
  • Smoking
  • Restricted areas
  • Hot works
  • Emergency arrangements

These are examples, not mandatory rules for every site.

Rules should be clear, brought to everyone’s attention and kept current; where relevant, consider communication and language needs, for example translated site rules. Sources: CDM 2015 regulation 12(2) (opens in a new tab); HSE L153 (opens in a new tab), Appendix 3, paragraph 13.

Information, induction and worker engagement

The checklist reviews whether the plan sets out how workers receive:

  • A suitable site induction
  • Information
  • Instruction
  • Supervision
  • Communication of relevant risks and controls

On a multi-contractor project, it also reviews worker cooperation, consultation and access to relevant information under Regulation 14, a Principal Contractor duty.

Sources: CDM 2015 regulation 13(4) (opens in a new tab), regulation 14 (opens in a new tab) and regulation 15(8) and (9) (opens in a new tab).

Welfare, access and emergency arrangements

The checklist reviews whether the plan reflects appropriate arrangements for:

  • Schedule 2 welfare facilities
  • Preventing unauthorised access
  • Safe access and movement, where relevant
  • Fire and emergency arrangements

It is not an emergency plan template or a site-security guide. Sources: CDM 2015 regulation 13(4) (opens in a new tab), regulation 15(9) to (11) (opens in a new tab) and Schedule 2 (opens in a new tab).

Focus on the significant construction-phase risks

The CPP should record the management arrangements for the significant health and safety risks associated with the construction phase.

This does not mean inserting a generic hazard library or full risk assessment into the plan.

The checklist reviews:

  • Project-specific risks
  • The controls and arrangements for them
  • Interfaces between contractors and work activities
  • Relevant PCI and design information
  • Changes to risks or controls

Source: HSE L153 (opens in a new tab), Appendix 3, paragraphs 3 and 5.

What is Schedule 3 in a Construction Phase Plan?

Where applicable, Regulation 12(2) requires the CPP to include specific measures concerning work falling within one or more Schedule 3 categories:

  1. 1. Particularly aggravated burial, engulfment or falling-from-height risk
  2. 2. Particular danger from chemical / biological substances or health monitoring
  3. 3. Ionising radiation requiring controlled / supervised areas
  4. 4. Work near high-voltage power lines
  5. 5. Drowning risk
  6. 6. Wells, underground earthworks and tunnels
  7. 7. Diving with an air supply
  8. 8. Compressed-air caissons
  9. 9. Explosives
  10. 10. Assembly / dismantling of heavy prefabricated components

If a Schedule 3 category does not apply, no Schedule 3-specific measure is required for that category solely under Regulation 12(2). Other significant project risks must still be managed appropriately.

Schedule 3 is not a complete list of construction risks.

Sources: CDM 2015 regulation 12(2) (opens in a new tab) and Schedule 3 (opens in a new tab). Summarised; see the Schedule for the full wording.

Is a Construction Phase Plan the same as RAMS?

No.

The Construction Phase Plan explains how health and safety will be managed across the construction phase.

Risk assessments and method statements address particular hazards, tasks or methods of work.

They can support each other, but one does not replace the other.

Source: HSE L153 (opens in a new tab), Appendix 3, paragraph 4.

How does the CPP relate to Pre-Construction Information?

Relevant Pre-Construction Information should inform preparation of the Construction Phase Plan.

On a multi-contractor project, the Principal Designer assists the Principal Contractor by providing relevant information it holds.

PCI is not the Construction Phase Plan.

Sources: CDM 2015 regulation 12(3) (opens in a new tab); HSE L153 (opens in a new tab), Appendix 3, paragraphs 7 and 12.

A plan needs to work in practice

The checklist reviews whether:

Sources: CDM 2015 regulation 13(3) (opens in a new tab) and regulation 15(3) (opens in a new tab); HSE L153 (opens in a new tab), Appendix 3, paragraphs 13 and 14.

  • Relevant people can access and understand the CPP
  • Contractors receive the parts relevant to their work
  • Site rules and induction reflect it
  • Changes are communicated
  • Feedback can be provided
  • Arrangements exist to check implementation

Completing this checklist is not evidence by itself that site conditions or controls are compliant in practice.

The Construction Phase Plan is a working document

On a multi-contractor project, the Principal Contractor must ensure the CPP is appropriately reviewed, updated and revised from time to time.

On a single-contractor project, the contractor should keep the plan fit for purpose as part of planning, managing and monitoring its work.

Sources: CDM 2015 regulation 12(4) (opens in a new tab) and regulation 15(2) (opens in a new tab); HSE L153 (opens in a new tab), Appendix 3, paragraphs 8(b) and 14.

The checklist prompts a review when something changes, including:

  • Design changes
  • Scope changes
  • Programme / sequencing changes
  • Construction method changes
  • A new contractor or work package
  • New risks or site conditions
  • An incident or near miss
  • Ineffective controls
  • New or changed Schedule 3 work
  • Welfare, access or emergency changes

No fixed weekly or monthly review interval

CDM 2015 does not prescribe a universal review cycle for the Construction Phase Plan.

Review frequency should reflect the project and changes in risks, work, design and the effectiveness of the arrangements.

How to use the checklist

  1. Step 1: Confirm who prepares the plan

    Identify whether the project is single- or multi-contractor and confirm the responsible contractor / Principal Contractor.

  2. Step 2: Review the plan

    Check that the CPP is project-specific, proportionate and clearly records the construction-phase arrangements and site rules.

  3. Step 3: Check risks and implementation

    Review significant risks, Schedule 3 where applicable, supporting information and how the arrangements are communicated.

  4. Step 4: Keep it current

    Record changes, outstanding actions and revisions as the project develops.

Who can use the checklist?

Anyone preparing, reviewing or relying on a Construction Phase Plan can use it.

  • Clients

    Check a plan is drawn up before the construction phase begins.

  • Principal Contractors

    Review the plan you draw up, maintain and revise.

  • Contractors on single-contractor projects

    Review the plan for your own work.

  • Principal Designers

    Check the information you provide has informed the plan.

  • CDM advisers

    Help duty holders review the plan and record actions.

  • Project managers

    Support the plan’s preparation and updates.

  • Construction managers

    Check the plan reflects how the site actually runs.

  • Health and safety professionals

    Review arrangements, site rules and significant risks.

  • Organisations reviewing CPP arrangements

    Record a consistent, evidence-based review.

  • Using an adviser or reviewer?

    They can help review the plan, but using an adviser or reviewer does not transfer statutory duties.

Construction Phase Plan Checklist FAQs

  • Is this Construction Phase Plan Checklist free?

    Yes. It is free to download, with no sign-up and no email address needed. Select Download the Word checklist and the file downloads straight away.

  • What format is the checklist?

    A Microsoft Word document (.docx) of 12 A4 pages, with no macros. It has project details on the first page, a set-up page, eleven numbered review sections including a Schedule 3 table, a practical final review, an outstanding actions table, key references and a completed / reviewed record. Each prompt is a Word content control, and each check has tick boxes with space for the evidence, reference or action. The document is not locked, so it can be adapted, printed, or saved as a PDF once completed.

  • Is a Construction Phase Plan required on every construction project?

    Yes. A Construction Phase Plan is required for every construction project to which CDM 2015 applies, including single-contractor and multi-contractor projects, whatever its size (regulation 4(5)(a) (opens in a new tab), regulation 12(1) (opens in a new tab) and regulation 15(5) (opens in a new tab)). It should be proportionate to the project.

  • Is a CPP required on a single-contractor project?

    Yes. On a single-contractor project, the contractor must draw up the plan, or arrange for it to be drawn up, as soon as is practicable before setting up the construction site (regulation 15(5) (opens in a new tab)). No Principal Designer or Principal Contractor appointment is needed where there is only one contractor.

  • Does a project need to be F10-notifiable to require a CPP?

    No. F10 notification is a separate Regulation 6 requirement (regulation 6 (opens in a new tab)), and notification status does not determine whether a Construction Phase Plan is required. The F10 Notification Calculator checks the notification thresholds.

  • Who prepares the Construction Phase Plan?

    On a multi-contractor project, the Principal Contractor draws up the plan or arranges for it to be drawn up (regulation 12(1) (opens in a new tab)). On a single-contractor project, the contractor does (regulation 15(5) (opens in a new tab)). The client must ensure a plan has been drawn up before the construction phase begins (regulation 4(5)(a) (opens in a new tab)). The Principal Designer assists the Principal Contractor by providing relevant information (regulation 12(3) (opens in a new tab)) but does not prepare or approve the plan.

  • When does the Construction Phase Plan need to be prepared?

    CDM 2015 sets three separate provisions. The client must ensure it is drawn up before the construction phase begins. The Principal Contractor draws it up during the pre-construction phase and before setting up the construction site. A single contractor draws it up as soon as is practicable before setting up the construction site.

  • Does the client have to approve the Construction Phase Plan?

    CDM 2015 does not prescribe a formal client approval certificate or CPP sign-off. The client must ensure the plan is drawn up before the construction phase begins and, on a multi-contractor project, take reasonable steps to ensure the Principal Contractor complies with Regulations 12 to 14 (regulation 4(6) (opens in a new tab)). HSE guidance says the client should ensure the plan adequately addresses the arrangements for managing the risks and is regularly reviewed and revised (L153 (opens in a new tab), Appendix 3, paragraph 8). Projects may still use internal or contractual review arrangements.

  • What should a Construction Phase Plan include?

    The health and safety arrangements for the construction phase, the site rules (taking account, where necessary, of industrial activities on the site) and, where applicable, specific measures for work in any Schedule 3 category (regulation 12(2) (opens in a new tab)). HSE guidance lists the project description, management arrangements and arrangements for controlling significant site risks (L153 (opens in a new tab), Appendix 3, paragraph 5). What is relevant depends on the project.

  • What does proportionate mean for a Construction Phase Plan?

    The level of detail should match the scale, complexity and risks of the project, while still being relevant and detailed enough to explain the arrangements, site rules and any special measures (L153 (opens in a new tab), Appendix 3, paragraph 4). A longer plan is not automatically a better plan, and a short, straightforward job may only need brief entries.

  • Should RAMS and risk assessments be included inside the CPP?

    Not indiscriminately. HSE guidance says the plan should not include documents that get in the way of a clear understanding of the arrangements, such as generic risk assessments, records of how decisions were reached or detailed safety method statements (L153 (opens in a new tab), Appendix 3, paragraph 4). Risk assessments, method statements and RAMS may still be necessary for particular work; they can be referenced where useful and support the plan without being copied into it.

  • What is Schedule 3 under CDM 2015?

    A list of ten categories of work involving particular risks, such as work near high-voltage power lines, work with explosives or work exposing workers to a risk of drowning (Schedule 3 (opens in a new tab)). Where applicable, the plan must include specific measures for that work (regulation 12(2) (opens in a new tab)). Where a category does not apply, no Schedule 3-specific measure is needed for it solely under Regulation 12(2), but other significant risks must still be managed. Schedule 3 is not a complete list of construction risks.

  • Is a Construction Phase Plan the same as RAMS?

    No. The Construction Phase Plan explains how health and safety will be managed across the construction phase. Risk assessments and method statements address particular hazards, tasks or methods of work. They can support each other, but one does not replace the other. See the RAMS Template and the Method Statement Template.

  • How often should the Construction Phase Plan be reviewed?

    CDM 2015 does not prescribe a fixed weekly, monthly or other review interval. The plan is a working document and should be reviewed regularly enough to address significant changes in the risks, the work, the design or the effectiveness of the controls (L153 (opens in a new tab), Appendix 3, paragraph 14).

  • Who updates the Construction Phase Plan during construction?

    On a multi-contractor project, the Principal Contractor must ensure the plan is appropriately reviewed, updated and revised from time to time (regulation 12(4) (opens in a new tab)). On a single-contractor project, the contractor keeps the plan fit for purpose as part of planning, managing and monitoring its work (regulation 15(2) (opens in a new tab); L153 (opens in a new tab), Appendix 3, paragraph 8(b)).

The template for preparing the plan, checklists for the duty holders and information it connects to, and templates for task-specific documents.

Review your Construction Phase Plan

Download the editable Word checklist and record the arrangements, risks, updates and outstanding actions that apply to your project.