Principal Designer duties under CDM 2015

The principal designer has a central role under CDM 2015 on projects involving more than one contractor. They lead health and safety during the pre-construction phase, coordinate designers, help manage foreseeable design risks and keep information flowing between the client, designers and principal contractor.

  • Published
  • Updated
  • 11 min read
Design team reviewing construction drawings during pre-construction planning

What is a Principal Designer under CDM 2015?

Under the Construction (Design and Management) Regulations 2015 (CDM 2015), the principal designer is the designer appointed by the client to take control of the pre-construction phase on a project involving, or likely to involve, more than one contractor. HSE guidance: principal designers, roles and responsibilities (opens in a new tab)

The role can be carried out by an organisation or an individual. The principal designer must be a designer as defined by CDM and must have the skills, knowledge and experience needed for the role, together with organisational capability where the appointment is an organisation. HSE guidance: are you a principal designer? (opens in a new tab)

The principal designer does not have to produce every design on the project. Their key function is to plan, manage, monitor and coordinate health and safety during the pre-construction phase and to make sure the design team works together to manage foreseeable risks.

Principal Designer duties: Regulation 11 at a glance

  1. Lead the pre-construction phase

    1. Step 1: Plan, manage and monitor

      Plan, manage and monitor the pre-construction phase and coordinate health and safety during it.

    2. Step 2: Apply the principles of prevention

      Take the general principles of prevention into account when design, technical and organisational decisions are made.

    3. Step 3: Identify and eliminate or control foreseeable risks

      So far as reasonably practicable, for those carrying out or affected by construction work, maintaining or cleaning the structure, or using it as a workplace.

  2. Direct the design team

    1. Step 4: Ensure designers comply

      Check designers meet their Regulation 9 duties, without producing or approving every design.

    2. Step 5: Secure cooperation and coordinate design

      Ensure everyone on the pre-construction phase cooperates with the client, the principal designer and each other.

  3. Share information

    1. Step 6: Assist with pre-construction information

      Help the client provide it, and pass it promptly to designers and contractors.

    2. Step 7: Liaise with the Principal Contractor

      Throughout the appointment, share information needed to plan and manage the construction phase.

Regulation 12 adds the health and safety file and helping the principal contractor with the construction phase plan. Each step links to the detail below.

When is a Principal Designer required?

A client must appoint a principal designer in writing where a construction project involves, or is likely to involve, more than one contractor. The appointment should be made as early as possible in the design process and, where practicable, at concept stage. Read Regulation 5 on legislation.gov.uk: appointment of the principal designer and the principal contractor (opens in a new tab)

This requirement is not limited to large or notifiable projects. A comparatively small refurbishment, maintenance or fit-out project may still require a principal designer if more than one contractor is involved or is likely to be involved.

If a commercial client fails to make the required appointment, the client takes on the principal designer duties that should have been allocated to the role. Read Regulation 5 on legislation.gov.uk: appointment of the principal designer and the principal contractor (opens in a new tab)

Need to make the appointment? Download our free one-page Principal Designer Appointment Letter.

What are the Principal Designer’s main duties?

The principal designer’s duties are centred on the pre-construction phase, but the role can continue into the construction phase where design work is still being developed or changed. In practice, the principal designer needs arrangements that allow them to remain involved for as long as their CDM functions are required.

The core duties include:

  • planning, managing, monitoring and coordinating health and safety in the pre-construction phase;
  • using relevant pre-construction information when coordinating design work;
  • helping the client assemble and provide pre-construction information;
  • working with designers to eliminate foreseeable risks where possible and reduce or control risks that remain;
  • ensuring designers cooperate, communicate and coordinate their work;
  • checking that designers are carrying out their CDM duties;
  • liaising with the principal contractor about design risks and information relevant to the construction phase; and
  • preparing, reviewing and updating the health and safety file where required.

Read Regulation 11 on legislation.gov.uk: duties of a principal designer in relation to health and safety at the pre-construction phase (opens in a new tab)

Plan, manage, monitor and coordinate the pre-construction phase

The principal designer must put suitable arrangements in place for managing health and safety during the pre-construction phase. This means more than holding occasional design meetings or collecting risk registers. Read Regulation 11 on legislation.gov.uk: duties of a principal designer in relation to health and safety at the pre-construction phase (opens in a new tab)

The arrangements should be proportionate to the scale, complexity and risks of the project and should support an effective design process. The principal designer needs sufficient visibility of the design work to identify where coordination is required, where information is missing and where significant or foreseeable risks need further attention.

In doing so, the principal designer must take account of the general principles of prevention, particularly when design, technical and organisational decisions are made about which stages of work will run at the same time or in sequence, and when estimating how long they will take. Where relevant, the content of any construction phase plan and health and safety file must also be taken into account. Read Regulation 11 on legislation.gov.uk: duties of a principal designer in relation to health and safety at the pre-construction phase (opens in a new tab)

Monitoring should also be active. If design decisions, interfaces or information flows are not being managed effectively, the principal designer should intervene and coordinate the people involved rather than simply record the issue.

Help the client with pre-construction information

The client is responsible for providing pre-construction information, but the principal designer has an important supporting role. They should help the client identify, assemble and distribute information that designers and contractors need to carry out their duties. HSE guidance: principal designers, roles and responsibilities (opens in a new tab)

Relevant information may include existing drawings, surveys, asbestos information, structural information, information about existing services, site constraints, access arrangements and an existing health and safety file.

The principal designer should also help identify gaps. Where information is missing but reasonably obtainable and necessary for safe design or planning, the project team should address that gap rather than allow design work to proceed on unsupported assumptions.

Our editable PCI Word template includes a register for recording significant information gaps, the action needed, an owner and a target date.

Coordinate designers and design work

One of the principal designer’s most important functions is to coordinate the design team. Individual designers retain their own CDM duties, but the principal designer must make sure their work is coordinated and that health and safety information is communicated between disciplines. Read Regulation 11 on legislation.gov.uk: duties of a principal designer in relation to health and safety at the pre-construction phase (opens in a new tab)

This is particularly important where one design affects another. Structural, architectural, mechanical, electrical, temporary works, specialist and contractor-designed elements can create interfaces that no single designer can manage in isolation.

Effective coordination may involve design reviews, risk workshops, clash or interface reviews, agreed design information requirements, action tracking and direct discussion between designers. The exact process should suit the project rather than become paperwork for its own sake.

Eliminate, reduce and control foreseeable design risks

CDM places duties on designers to eliminate foreseeable health and safety risks where reasonably practicable and, where risks cannot be eliminated, to reduce or control them. The principal designer must coordinate this process across the design team. Read Regulation 9 on legislation.gov.uk: duties of designers (opens in a new tab)

The aim is not to produce a design with no risk. Construction, maintenance, use and eventual demolition will always involve risk. The principal designer should instead focus attention on significant and foreseeable risks that can be influenced through design.

Examples might include access for installation and maintenance, structural stability during sequencing, heavy or difficult-to-handle components, work at height, existing services, confined spaces, future cleaning and maintenance access, or interfaces between different systems.

The principal designer should also avoid encouraging indiscriminate design-risk paperwork. Information should be proportionate and useful to those who need it, particularly where a residual risk is unusual, significant or not likely to be obvious to a competent contractor. HSE designer guidance: designers, roles and responsibilities (opens in a new tab)

Worked example: coordinating rooftop plant replacement

Worked example

  1. Design issue

    Replacement rooftop plant is proposed in a position that would make installation access difficult and create future maintenance risks.

  2. Principal Designer coordination

    The principal designer brings together the architectural, structural and building-services designers, reviews the available pre-construction information and challenges whether the risk can be eliminated or reduced through the design.

  3. Design response

    The designers review the plant location, permanent access, lifting strategy and maintenance clearances. Where reasonably practicable, they revise the design to reduce installation and future maintenance risk.

  4. Information and handover

    Significant residual risk information is shared with the principal contractor and, where it will be needed for future work, identified for the health and safety file.

Illustrative example only. The appropriate design response depends on the project and what is reasonably practicable.

Key takeaway

The principal designer’s role is to lead and coordinate how health and safety is managed through design and pre-construction, not to personally design every solution.

Ensure designers comply with their duties

The principal designer is expected to take reasonable steps to ensure designers on the project comply with their CDM duties. That does not mean the principal designer becomes responsible for producing or approving every design on behalf of each designer. Read Regulation 11 on legislation.gov.uk: duties of a principal designer in relation to health and safety at the pre-construction phase (opens in a new tab)

It does mean they need enough oversight to identify whether designers are considering pre-construction information, applying the general principles of prevention, coordinating with others and communicating information about significant residual risks.

Where a designer is not meeting those expectations, the principal designer should raise the issue and coordinate the action needed to address it.

Liaise with the Principal Contractor

The principal designer and principal contractor have different areas of control, but their duties overlap at the interface between design and construction. The principal designer should liaise with the principal contractor and provide information about design matters and risks that need to be managed during the construction phase. Read Regulation 11 on legislation.gov.uk: duties of a principal designer in relation to health and safety at the pre-construction phase (opens in a new tab)

The principal contractor can also provide valuable construction knowledge back into the design process, particularly around sequencing, temporary works, access, logistics and buildability. Good CDM coordination should therefore work in both directions rather than treating design and construction as separate silos. HSE principal contractor guidance: principal contractors, roles and responsibilities (opens in a new tab)

Where design continues during construction, this liaison becomes particularly important because the pre-construction phase can continue for those elements even after physical construction has started.

Prepare and update the health and safety file

For projects involving more than one contractor, the principal designer is normally responsible for preparing the health and safety file during the project. The file should contain information likely to be needed to protect health and safety during future construction work, such as maintenance, refurbishment or demolition. Read Regulation 12 on legislation.gov.uk: construction phase plan and health and safety file (opens in a new tab)

The file should be developed as the project progresses rather than assembled as an afterthought at handover. Information should be relevant, proportionate and useful for future work.

If the principal designer’s appointment ends before the end of the project, responsibility for the file passes to the principal contractor, who must then complete it and pass it to the client. Read Regulation 12 on legislation.gov.uk: construction phase plan and health and safety file (opens in a new tab)

How long does the Principal Designer role last?

The principal designer should remain appointed for as long as they are needed to carry out the role. Although the title focuses on the pre-construction phase, design work often continues after construction has begun. HSE guidance: principal designers, roles and responsibilities (opens in a new tab)

A client should therefore avoid ending the appointment automatically at the start of site work if significant design coordination remains. The scope and duration of the appointment should reflect the actual project and the design work still to be completed.

What skills, knowledge and experience does a Principal Designer need?

The principal designer must have the skills, knowledge and experience necessary to carry out the role in a way that secures health and safety. Where the principal designer is an organisation, it must also have the organisational capability needed for the project. Read Regulation 8 on legislation.gov.uk: general duties, including skills, knowledge and experience (opens in a new tab)

The level required should be proportionate to the project. A complex infrastructure, high-rise or technically unusual project will require different capability from a straightforward small refurbishment.

Relevant evidence might include experience of comparable projects, technical construction knowledge, understanding of design risk management and CDM, competent people within the organisation, suitable processes and resources, and relevant continuing professional development.

CDM Principal Designer vs Building Regulations Principal Designer

The term “principal designer” is now used in two different legal frameworks in England, so it is important not to assume the roles are interchangeable.

This guide covers the principal designer role under CDM 2015, which is focused on managing health and safety during the pre-construction phase of construction projects.

A separate principal designer role exists under the Building Regulations framework. That role has different legal functions relating to compliance with the Building Regulations. The same person or organisation may sometimes hold both appointments where they are competent and properly appointed for each role, but one appointment does not automatically satisfy the other.

Principal Designer duties checklist

As a practical sense-check, a CDM principal designer should be able to demonstrate arrangements covering the following:

Appointment and capability

  • The appointment is clear, in writing and made early enough to influence the project.
  • The scope and duration of the principal designer role match the design work required.
  • There is suitable evidence that the principal designer has the skills, knowledge, experience and organisational capability required for the project.

Pre-construction information

  • Relevant pre-construction information has been identified, reviewed and shared.
  • Gaps in important project information are identified and managed.

Design coordination

  • Designers understand their CDM duties and cooperate with one another.
  • Design interfaces and significant foreseeable risks are actively coordinated.
  • Design changes during construction continue to be coordinated where required.

Design risk

  • Designers are taking reasonable steps to eliminate, reduce or control foreseeable risks.
  • Significant residual risk information is communicated in a useful and proportionate way.

Liaison and the health and safety file

  • There is effective liaison with the client and principal contractor.
  • The health and safety file is being developed as the project progresses.

A checklist can support governance, but it does not replace professional judgement. The arrangements need to reflect the project, the design team and the risks involved.

Common Principal Designer mistakes

Treating the role as a document-management exercise

Collecting risk registers and meeting minutes is not the same as coordinating health and safety through design. The role needs active involvement in how designers communicate, make decisions and manage significant foreseeable risks.

Being appointed too late

If the principal designer joins after key design decisions have already been fixed, opportunities to eliminate or reduce risk may already have been lost. Early appointment gives the role meaningful influence.

Assuming every design risk must be transferred to the contractor

Designers should first consider whether foreseeable risks can be eliminated or reduced through design. Residual information should focus on what others genuinely need to know, rather than shifting every possible risk into notes and registers.

Ending the appointment when site work starts

The pre-construction phase can continue for design work carried out during construction. The appointment should reflect the real duration of the principal designer’s functions.

Confusing the CDM and Building Regulations roles

Using the same title for two legal roles can create gaps in responsibility. Appointment documents and project governance should distinguish clearly between them.

Frequently asked questions

  • What are the duties of a Principal Designer under CDM 2015?

    The principal designer plans, manages, monitors and coordinates health and safety during the pre-construction phase. They help the client with pre-construction information, coordinate designers and design risks, ensure designers cooperate and carry out their duties, liaise with the principal contractor and prepare the health and safety file. The Regulation 11 summary sets these out step by step.

  • What does a Principal Designer actually do on a project?

    The principal designer leads and coordinates how health and safety is managed during the pre-construction phase. In practice, that means planning and monitoring pre-construction work, bringing designers together, making sure foreseeable risks are considered through the design, managing relevant information and liaising with the principal contractor. The role is not simply to collect risk registers or approve every design.

  • Is the Principal Designer responsible for all design risk?

    No. Each designer keeps their own Regulation 9 duties for the risks arising from their design. The principal designer coordinates how foreseeable risks are identified and eliminated or controlled across the design team, and must ensure designers comply with their duties, but that coordination role does not transfer each designer’s responsibility to the principal designer.

  • Does the Principal Designer approve designers’ work?

    Not in the sense of producing or signing off every design. The principal designer must ensure designers comply with their duties, which in practice means appropriate checks, design reviews and challenge where significant risks are not being addressed. Each designer remains responsible for their own design.

  • How does the Principal Designer work with the Principal Contractor?

    The principal designer must liaise with the principal contractor for the duration of their appointment and share information relevant to planning, managing and monitoring the construction phase, including what the principal contractor needs for the construction phase plan. Liaison continues where design work carries on during construction. See liaising with the Principal Contractor and Principal Designer vs Principal Contractor.

  • Does the Principal Designer prepare the pre-construction information?

    The client is responsible for providing pre-construction information. The principal designer must assist the client with it and, so far as it is within their control, provide it promptly and in a convenient form to designers and contractors who are appointed or being considered for appointment.

  • Does every construction project need a Principal Designer?

    No. A principal designer is required where a project involves, or is likely to involve, more than one contractor. Single-contractor projects do not require a principal designer appointment under CDM 2015.

  • Can the Principal Designer be an individual?

    Yes. The role can be carried out by an individual or organisation that meets the definition of designer and has the skills, knowledge and experience, and where relevant organisational capability, needed for the project. It does not have to be an architect. See who can be a Principal Designer.

  • Can the Principal Designer be the same organisation as another dutyholder?

    Potentially, yes. CDM does not require every dutyholder role to be held by a separate organisation. What matters is that the organisation is properly appointed where required, is capable of carrying out each role and has arrangements to manage any conflicts or gaps in responsibility.

  • Does the Principal Designer role end when construction starts?

    Not necessarily. Design work frequently continues during construction, and the principal designer may need to remain appointed while pre-construction functions and design coordination are still required.

  • Is the Principal Designer responsible for the health and safety file?

    Yes, on projects involving more than one contractor. The principal designer normally prepares and develops the health and safety file on projects involving more than one contractor. If their appointment ends before project completion, the principal contractor takes over responsibility for completing the file and passing it to the client.

  • Is the CDM Principal Designer the same as the Building Regulations Principal Designer?

    No. They are separate legal roles with different functions. The same person or organisation may sometimes hold both roles if properly appointed and competent for each, but the appointments should be treated separately.

Need CDM training?

Learn the core requirements, then follow a pathway based on your responsibilities.

Explore CDM training
  • Topic hub

    CDM hub

    Plain-English CDM 2015 guidance, free tools, checklists and role-relevant training in one place.

  • Checklists

    CDM checklists

    Working checklists for common duty-holder tasks, including Principal Designer duties and pre-construction information.

    More free CDM checklists are available in our checklist library, including the Principal Designer Duties Checklist.

  • Free tools

    Free tools

    Try the Does CDM Apply? checker and explore more free CDM tools as they become available.

    Guidance only. Not legal advice or a definitive compliance determination.

View all guides
  • Construction project team coordinating responsibilities under CDM 2015

    Topic: CDM

    CDM duty holders explained

    CDM 2015 gives legal duties to the people and organisations that can influence how construction work is planned, designed and delivered. These people are commonly referred to as CDM duty holders.

    11 min read
  • Designer reviewing digital construction drawings and technical design information

    Topic: CDM

    CDM designer duties explained

    Designers have a direct legal role under the Construction (Design and Management) Regulations 2015 (CDM 2015). Their decisions can influence the risks faced not only by the people who build a project, but also by those who use, maintain, clean, refurbish and eventually demolish it.

    11 min read
  • Construction project team reviewing information on site under CDM 2015

    Topic: CDM

    CDM client duties explained

    Clients have one of the most influential roles under CDM 2015. They set the budget, programme and procurement approach, appoint the project team and create the conditions in which health and safety will be managed. This guide explains the main CDM client duties and what they look like in practice.

    11 min read
  • Construction management team coordinating work on site during the construction phase

    Topic: CDM

    Principal Contractor duties explained

    The Principal Contractor leads health and safety during the construction phase on projects involving more than one contractor. Under CDM 2015, the role goes well beyond producing a construction phase plan: it includes planning, managing, monitoring and coordinating the work, organising contractors, providing suitable site arrangements and keeping the client and Principal Designer informed.

    9 min read

Stay up to date

Get new guides straight to your inbox.

Be the first to know when we publish new guidance, tools and resources.

See our privacy notice for how we handle your details.