A practical, editable Word checklist for reviewing the Principal Designer’s key duties during the pre-construction phase under CDM 2015.

  • For Principal Designers on projects with more than one contractor
  • Covers Regulations 11 and 12: design risk, designers, PCI, CPP information and the H&S File
  • Records evidence, references and outstanding actions
  • A practical review aid, not a statutory form or technical design approval checklist
Download the Word checklist (Word document, 244 KB, Aptoris-Principal-Designer-Duties-Checklist.docx)

Editable .docx, 10 pages, No sign-up required

Read the Principal Designer Duties guide
  • Pre-construction managementReview how health and safety is being planned, managed, monitored and coordinated during the pre-construction phase.
  • Design risk & designersCheck how foreseeable design risks and designers’ duties under Regulation 9 are being managed.
  • Information & liaisonReview Pre-Construction Information, Principal Contractor liaison and information needed for the Construction Phase Plan.
  • H&S File & actionsTrack Health and Safety File arrangements, evidence, references and outstanding Principal Designer actions.

What are the Principal Designer’s duties under CDM 2015?

The Principal Designer plans, manages, monitors and coordinates health and safety during the pre-construction phase on projects where more than one contractor is involved or reasonably foreseeable. The key duties include:

  • Planning, managing and monitoring the pre-construction phase
  • Coordinating health and safety matters
  • Taking account of the general principles of prevention
  • Identifying foreseeable risks
  • Eliminating risks so far as is reasonably practicable
  • Reducing or controlling risks that cannot be eliminated
  • Ensuring designers comply with Regulation 9
  • Ensuring those working in the pre-construction phase cooperate
  • Assisting the client with Pre-Construction Information
  • Providing relevant PCI promptly, where within its control
  • Liaising with the Principal Contractor
  • Providing relevant information for the Construction Phase Plan
  • Preparing and maintaining the Health and Safety File

This is a summary, not a substitute for the Regulations. Sources: CDM 2015 regulations 11 (opens in a new tab) and 12 (opens in a new tab), with the relevant parts of regulation 8 (opens in a new tab) and regulation 9 (opens in a new tab); HSE Principal designers: roles and responsibilities (opens in a new tab); HSE L153 Managing health and safety in construction (opens in a new tab). The Principal Designer Duties guide explains each duty in more detail.

When is a Principal Designer required?

Where more than one contractor will work on the project, or it is reasonably foreseeable that more than one contractor will work on it, the client must appoint in writing a designer with control over the pre-construction phase as Principal Designer.

The appointment must be made as soon as practicable and, in any event, before the construction phase begins. HSE encourages early appointment, when the Principal Designer has the most opportunity to influence design risk.

Principal Designer Appointment Letter

Source: CDM 2015 regulation 5 (opens in a new tab). See the Principal Designer appointment guide.

What if there is only one contractor?

Where only one contractor is involved, Regulation 5 does not require a Principal Designer appointment solely because of contractor count. Designers still have their own duties under Regulation 9.

Designer duties under CDM 2015

Who can be the Principal Designer?

The Principal Designer must be a designer with control over the pre-construction phase. HSE describes it as the designer appointed by the client to take control of the pre-construction phase.

That does not automatically mean:

  • The architect
  • The organisation producing the most drawings
  • The party with contractual authority over every consultant

The appointee needs the skills, knowledge, experience and, for an organisation, the organisational capability to carry out the role on that project.

Sources: CDM 2015 regulation 5(1)(a) (opens in a new tab) and regulation 8(1) (opens in a new tab); HSE Principal designers (opens in a new tab). See who can be a Principal Designer.

Preview the Principal Designer Duties Checklist

Ten pages: project details and role set-up, eleven numbered duty sections, a practical final review, outstanding Principal Designer actions and a completed / reviewed record.

These are real pages from the Word checklist. Each check has tick boxes for Done (or Reviewed / current, for ongoing duties) and N/A, with space for the evidence, reference or action behind it. The blue guidance box can be deleted before issue.

Page with section 2, identify, eliminate and control foreseeable risks, with rows for construction, maintenance and cleaning, workplace use, identify, eliminate, reduce or control and residual information, a note that CDM 2015 does not prescribe a Design Risk Register format, a design-risk and coordination reference field, and the start of section 3, designer duties and compliance
Foreseeable risks and designer dutiesOpen full-size page: Foreseeable risks and designer duties (opens in a new tab)

Section 2 · Identify, eliminate and control foreseeable risks

Foreseeable risks and designer duties

  • Risks to people carrying out or affected by construction work
  • Risks to people maintaining or cleaning the structure, or using it as a workplace
  • Identify, eliminate, then reduce or control so far as is reasonably practicable
  • Significant residual information needed by others

Swipe to see more pages.

Final page finishing the practical final review, then an outstanding Principal Designer actions table with columns for reference, action, responsible person or organisation, target date and complete, five starter rows, and a completed and reviewed by record
Final review and actionsOpen full-size page: Final review and actions (opens in a new tab)

Final review · Outstanding Principal Designer actions

Final review and actions

  • A practical final review, labelled not a statutory checklist
  • Outstanding actions with a responsible person, target date and completion
  • Five starter action rows; add more with Insert Row
  • Completed by, and reviewed / updated by where the project requires it

What the checklist covers

A project and role set-up page, the Principal Designer’s duties in order, then a practical final review, outstanding actions and a completed / reviewed record.

  • Project and role set-up
  • Plan, manage, monitor and coordinate the pre-construction phase
  • General principles of prevention
  • Identify, eliminate and control foreseeable risks
  • Designer duties and Regulation 9 compliance
  • Cooperation and coordination
  • Pre-Construction Information
  • Liaison with the Principal Contractor
  • Information for the Construction Phase Plan
  • Health and Safety File
  • Where the Principal Designer also carries out design work
  • Appointments and capability
  • Keep arrangements current
  • Practical final review
  • Outstanding Principal Designer actions
  • Completed / reviewed record

Manage health and safety during the pre-construction phase

This is the core Principal Designer duty in regulation 11(1)⁠–⁠(2) (opens in a new tab): planning, managing and monitoring the pre-construction phase and coordinating health and safety matters so that, so far as is reasonably practicable, the project is carried out without risks to health or safety.

It reviews the management arrangements; it is not a design audit.

The checklist asks whether arrangements cover:

  • Planning health and safety in the pre-construction phase
  • Clear, proportionate management arrangements
  • Monitoring whether the arrangements work in practice
  • Coordinating designers and others involved
  • Design, technical and organisational decisions
  • Work taking place at the same time or in succession
  • The time needed for work and work stages
  • The general principles of prevention
  • Relevant existing Construction Phase Plan or Health and Safety File information

Apply the general principles of prevention

The Principal Designer must take the general principles of prevention into account when planning, managing, monitoring and coordinating the pre-construction phase, particularly when design, technical and organisational decisions are made and when time is being estimated.

  • Avoid risks where possible
  • Combat risks at source
  • Adapt to technical progress
  • Give collective protection priority over individual measures

Sources: regulation 11(2) (opens in a new tab); the principles are set out in Schedule 1 to the Management of Health and Safety at Work Regulations 1999 (opens in a new tab).

Identify, eliminate and control foreseeable risks

In fulfilling its duties, the Principal Designer must identify and eliminate or control, so far as is reasonably practicable, foreseeable risks to the health or safety of people (regulation 11(3) (opens in a new tab)):

  • Carrying out construction work
  • Liable to be affected by construction work
  • Maintaining or cleaning the structure
  • Using the structure as a workplace, where relevant

Foreseeable risks should be eliminated so far as is reasonably practicable. Where they cannot be eliminated, they should be reduced or controlled so far as is reasonably practicable.

Significant residual information that others need, such as designers, contractors and the Principal Contractor, should be communicated appropriately and proportionately.

The checklist works at the level of the project’s actual design, not a generic hazard list.

Is a Design Risk Register required by CDM?

No particular Design Risk Register format is prescribed by CDM 2015.

A register can be a useful project tool where it supports proportionate design-risk management, coordination and communication. Not every residual risk needs a drawing note or a register entry: the aim is information that others genuinely need.

Design Risk Register Template

See the Design Risk Register guide.

Ensure designers comply with Regulation 9

The Principal Designer must ensure all designers comply with their duties in regulation 9 (opens in a new tab) (regulation 11(4) (opens in a new tab)). Each designer keeps its own duties. The checklist reviews the arrangements for:

  • Client-duty awareness before design work starts
  • Relevant Pre-Construction Information
  • The general principles of prevention
  • Eliminating foreseeable risks so far as is reasonably practicable
  • Reducing or controlling risks where elimination is not possible
  • Relevant residual-risk information to the Principal Designer
  • Health and Safety File information
  • Sufficient design, construction and maintenance information

See designer duties under CDM 2015.

Does the Principal Designer have to approve every design?

CDM 2015 does not create a universal requirement for the Principal Designer to technically approve or sign off every design or check every designer’s calculations.

The Principal Designer must ensure designers comply with their CDM duties and coordinate health and safety during the pre-construction phase. Projects may use technical design reviews or approvals for separate contractual or professional reasons.

CDM 2015 does not require a particular design risk assessment form or risk matrix either: evidence of how foreseeable risk is managed can take different forms.

Sources: CDM 2015 regulation 9 (opens in a new tab) and regulation 11(4) (opens in a new tab).

Coordinate designers and design interfaces

People working in relation to the pre-construction phase must cooperate with the client, the Principal Designer and each other. The checklist prompts a review of whether:

  • Interfaces between design disciplines are coordinated
  • Relevant changes reach the people affected
  • Material information gaps or conflicts are followed up
  • Relevant construction knowledge is obtained where it would inform design decisions

Sources: regulation 11(5) (opens in a new tab) and regulation 8(4) (opens in a new tab). CDM 2015 does not require BIM, a common data environment, particular software or a meeting frequency.

Assist the client with Pre‑Construction Information

The client remains responsible for providing Pre-Construction Information. The Principal Designer:

  • Assists the client in providing it
  • Considers relevant information already held, including any existing Health and Safety File
  • Identifies material information gaps and raises them with the client
  • So far as within its control, provides PCI promptly and in a convenient form to designers and contractors appointed or being considered

Source: regulation 11(6) (opens in a new tab). Raising a gap does not mean the Principal Designer must commission or pay for every survey itself. See the Pre-Construction Information Template and guide.

Liaise with the Principal Contractor

For the duration of its appointment, the Principal Designer:

  • Liaises with the Principal Contractor
  • Shares information relevant to planning, managing and monitoring the construction phase
  • Shares information relevant to coordinating health and safety during construction
  • Keeps coordinating design development during construction while it remains appointed
  • Considers construction feedback that affects ongoing design or pre-construction matters

Source: regulation 11(7) (opens in a new tab). Not every project communication has to pass through the Principal Designer.

Provide information for the Construction Phase Plan

The Principal Designer must provide the Principal Contractor with information it holds that is relevant to the Construction Phase Plan, including:

  • Relevant Pre-Construction Information obtained from the client
  • Relevant information obtained from designers
  • Relevant design development

Source: regulation 12(3) (opens in a new tab). The Principal Designer supports the Principal Contractor with relevant information; the statutory duty to draw up or arrange the Construction Phase Plan on a multi-contractor project remains with the Principal Contractor. See the Construction Phase Plan Template.

Prepare and maintain the Health and Safety File

On a project with a Principal Designer, the Principal Designer:

  • Prepares the file during the pre-construction phase
  • Makes it appropriate to the characteristics of the project
  • Includes information likely to be needed for future work to protect health and safety
  • Reviews, updates and revises it as the work develops and changes occur
  • Incorporates relevant information provided by the Principal Contractor
  • Passes it to the Principal Contractor if its appointment ends before the project does
  • Passes it to the client at the end of the project if it remains appointed

The file is not a store for every project record, an O&M manual or generic RAMS.

Source: regulation 12(5), (6), (8) and (10) (opens in a new tab). See the Health and Safety File Template and guide.

The Principal Designer may also be a designer

Where the Principal Designer prepares or modifies designs, its own Regulation 9 designer duties apply in addition to its Principal Designer duties. Section 9 of the checklist is a short reminder of them, kept separate from the Principal Designer’s role of ensuring other designers comply.

Sources: CDM 2015 regulation 9 (opens in a new tab); the Principal Designer is a designer appointed under regulation 5(1)(a) (opens in a new tab).

Take reasonable steps when making appointments

Where the Principal Designer itself appoints designers, contractors or others to work on the project, it must take reasonable steps to satisfy itself that they have what the work needs (regulation 8(3) (opens in a new tab)). Checks should be proportionate to the work and risks.

CDM 2015 does not prescribe ISO certification, an SSIP scheme, insurance scoring or a points system.

The Principal Designer itself must have the skills, knowledge, experience and organisational capability needed for the role (regulation 8(1) and (2) (opens in a new tab)). See competence under Regulation 8.

The checklist prompts the Principal Designer to consider:

  • Skills
  • Knowledge
  • Experience
  • Organisational capability, where an organisation is appointed
  • The scope of the appointment
  • Time and resources for the work
  • A reasonable basis for the appointment

Review arrangements when the project changes

There is no universal fixed review frequency. The checklist prompts a review when something changes, for example:

  • New designers
  • Relevant new contractors
  • Design changes
  • Scope changes
  • Programme changes
  • Sequencing changes
  • New PCI
  • Construction feedback
  • CPP information changes
  • H&S File information
  • Changes in PD / PC interfaces

CDM 2015 does not prescribe a universal weekly or monthly Principal Designer review frequency.

What changes on a domestic‑client project?

On a domestic-client project involving more than one contractor, a Principal Designer is still required. If the domestic client does not make the required appointment, the designer in control of the pre-construction phase becomes the Principal Designer.

The Principal Designer may also agree in writing to carry out the domestic client’s transferred client duties. Those client duties are separate from the Principal Designer duties covered by this checklist.

Source: CDM 2015 regulation 7 (opens in a new tab). Use the CDM Client Duties Checklist for the client duties.

CDM Principal Designer vs Building Regulations Principal Designer

This checklist covers the Principal Designer role under CDM 2015. In England, the Principal Designer under the Building Regulations is a legally distinct role with separate duties, even where the same organisation holds both appointments.

Sources: CDM 2015 regulation 5 (opens in a new tab); Building Regulations 2010 regulation 11D (opens in a new tab).

How to use the checklist

  1. Step 1: Confirm the role

    Confirm the Principal Designer appointment, project contractor arrangements and control of the pre-construction phase.

  2. Step 2: Review the arrangements

    Work through pre-construction management, design risk, designer coordination, PCI, CPP information and Health and Safety File arrangements.

  3. Step 3: Record evidence and actions

    Use the evidence / reference / action fields to record project documents, design coordination records or gaps requiring attention.

  4. Step 4: Keep it current

    Review relevant sections when design, scope, programme, information or project arrangements materially change.

Who can use the checklist?

Anyone reviewing or supporting the Principal Designer’s CDM 2015 duties on a project can use it.

  • Principal Designer organisations

    Review your arrangements early in design and as the project develops.

  • Principal Designer leads

    Check the arrangements you lead and record the evidence behind them.

  • Architects acting as PD

    Keep the Principal Designer role distinct from your own design work.

  • Engineering consultancies acting as PD

    Apply a consistent review across disciplines and projects.

  • Design managers

    See how design risk, interfaces and information flows are being coordinated.

  • CDM advisers supporting the PD

    Help the Principal Designer review its duties and record the basis for its arrangements.

  • Organisations preparing for appointment

    Understand what the Principal Designer role will involve before taking it on.

  • Using an adviser?

    An adviser can help review the arrangements and record the evidence, but using an adviser does not transfer the Principal Designer’s duties.

Principal Designer Duties Checklist FAQs

  • Is this Principal Designer Duties Checklist free?

    Yes. It is free to download, with no sign-up and no email address needed. Select Download the Word checklist and the file downloads straight away.

  • What format is the checklist?

    A Microsoft Word document (.docx) of 10 A4 pages, with no macros. It has project details on the first page, a project and role set-up page, eleven numbered duty sections, a practical final review, an outstanding Principal Designer actions table and a completed / reviewed record. Each prompt is a Word content control, and each check has tick boxes for Done (or Reviewed / current) and N/A with space for the evidence, reference or action. The document is not locked, so it can be adapted, printed, or saved as a PDF once completed.

  • What are the Principal Designer’s main duties under CDM 2015?

    To plan, manage and monitor the pre-construction phase and coordinate health and safety matters during it (regulation 11 (opens in a new tab)). That includes identifying and eliminating or controlling foreseeable risks, ensuring designers comply with their duties, ensuring cooperation, assisting the client with Pre-Construction Information and liaising with the Principal Contractor, as well as providing information for the Construction Phase Plan and preparing the Health and Safety File (regulation 12 (opens in a new tab)).

  • When is a Principal Designer required?

    Where more than one contractor will work on the project, or it is reasonably foreseeable that more than one contractor will work on it (regulation 5 (opens in a new tab)). Where only one contractor is involved, Regulation 5 does not require a Principal Designer appointment for that reason; designers still have their own duties under Regulation 9.

  • Who appoints the Principal Designer?

    The client, in writing, as soon as practicable and before the construction phase begins (regulation 5 (opens in a new tab)). If a client required to appoint a Principal Designer does not do so, the client must fulfil the Principal Designer’s duties itself. If a domestic client does not make the appointment, the designer in control of the pre-construction phase is the Principal Designer (regulation 7(2) (opens in a new tab)). The Principal Designer Appointment Letter can be used to record the appointment.

  • Who can act as Principal Designer?

    A designer with control over the pre-construction phase, which can be an organisation or, on smaller projects, an individual. It does not automatically have to be the architect or the designer producing the most drawings, and it must have the skills, knowledge, experience and, for an organisation, the organisational capability for the role (regulation 8 (opens in a new tab)). See who can be a Principal Designer.

  • Does the Principal Designer have to approve every design?

    No. CDM 2015 does not create a universal requirement for the Principal Designer to technically approve or sign off every design or check every designer’s calculations. The Principal Designer must ensure designers comply with their CDM duties and coordinate health and safety during the pre-construction phase. Projects may use technical design reviews or approvals for separate contractual or professional reasons.

  • Is a Design Risk Register legally required?

    No particular Design Risk Register format is prescribed by CDM 2015, and neither is a particular design risk assessment form or risk matrix. A register can still be a useful project tool where it supports proportionate design-risk management, coordination and communication: see the Design Risk Register Template.

  • What does the Principal Designer do with Pre-Construction Information?

    The client is responsible for providing it. The Principal Designer must assist the client and, so far as it is within its control, provide Pre-Construction Information promptly and in a convenient form to every designer and contractor appointed, or being considered for appointment (regulation 11(6) (opens in a new tab)). The Pre-Construction Information Template gives a structure for it.

  • What information does the Principal Designer provide for the Construction Phase Plan?

    All the information it holds that is relevant to the plan, including Pre-Construction Information obtained from the client and information obtained from designers about risks they could not eliminate (regulation 12(3) (opens in a new tab)). The Principal Contractor draws up the plan, or arranges for it to be drawn up.

  • Who prepares the Health and Safety File?

    On a project with a Principal Designer, the Principal Designer prepares it during the pre-construction phase and keeps it reviewed, updated and revised (regulation 12(5) and (6) (opens in a new tab)). The Principal Contractor provides relevant information for it. At the end of the project, the Principal Designer passes the file to the client.

  • What happens if the Principal Designer’s appointment ends before the project is complete?

    The Principal Designer must pass the Health and Safety File to the Principal Contractor, which must then keep it reviewed, updated and revised and pass it to the client at the end of the project (regulation 12(8)⁠–⁠(10) (opens in a new tab)).

  • Can the Principal Designer also carry out design work?

    Yes. The Principal Designer is a designer. Where it prepares or modifies designs, its own duties under regulation 9 (opens in a new tab) apply in addition to its Principal Designer duties. Section 9 of the checklist is a short reminder of them.

  • Is the CDM Principal Designer the same as the Building Regulations Principal Designer?

    No. In England, the Principal Designer under the Building Regulations (regulation 11D (opens in a new tab)) is a legally distinct role with separate duties, even where the same organisation holds both appointments. This checklist covers the CDM 2015 role only.

Guidance, templates and checklists for the duties the checklist reviews.

Review the Principal Designer’s duties on your next project

Download the editable Word checklist and record the arrangements, evidence and outstanding actions that apply.